Some Critical Issues Pertaining to Road Construction Industry

Some Critical Issues Pertaining to Road Construction Industry

H. L. Chawla, Consultant, World Bank

During the course of inspections carried out by me as a part of various World Bank missions on the National Highways, State Highways and other road construction projects in the country, I have tried to find out the various constraints affecting the progress of the construction of the roads. Some of the critical issues pertaining to the Indian Road Construction Industry are as under:
  • Pre-construction issues
  • Land surveying, investigations and design issues
  • Construction and contract management issues

Pre-construction issues:

  • Delay in land acquisition
  • Resettlement of project affected persons
  • Tree cutting
  • Shifting of utilities
Since encumbrance free site is not made available to the contractors in the initial stages of the project, the contractors delay the mobilization and in most of the cases, the contractors use the mobilization advance elsewhere.

One more reason is that the extent of land to be acquired is not possible to be identified because of the outdated land records and poor quality of designs. Sometimes additional land requirements become necessary to take care of the designed right of way.

Another reason is that the trees to be cut are not properly demarcated on the design drawings. Moreover, the clearances and permissions from the Ministry of Environment and Forests is a pre-requisite and takes quite some time before the trees are cut and design right of way made available to the contractors.

Since no proper records exist of the under ground utilities like water supply, sewerage lines, electrical and telephone cables etc., these utilities get identified as encumbrance only during the implementation stage of the project. Similarly shifting of overhead electrical and telephone lines (which are visible including poles) takes a long time. This leads to delay as the shifting of these utilities brings in hardships to the general population and suitable alternate arrangements are required to be made.

Some Critical Issues Pertaining to Road Construction Industry
There are numerous government agencies involved from which clearances/approvals/permissions are required to be obtained before the utilities can be shifted or relocated. This takes a great deal of time. There are cumbersome procedures involved and sometimes the relevant laws and regulations are also not very clear.

The delay in the handing over of the encumbrance-free land to the contractor generally takes as much as about 30 months compared to about 20 months which should have been the ideal case. Even when the land was finally made available, there exist still some encumbrances which put a constraint on the contractor’s capacity to undertake construction work in an un-interrupted and continuous manner. Because of the above reasons, substantial extensions of time are required to be given to the contractors.

These time over runs lead to cost over runs. These also lead to claims by the contractors for idle resources and demand for compensation.

Land Surveying, Investigations, and Design Issues

The land acquisition for the highway projects is carried out in accordance with the principles laid out in the National Highways Act or the Land Acquisition Act. These two Acts govern the acquisition of land for defined public purposes and compensation in lieu thereof. If all due processes are followed, the land acquisition as per the NH act should normally take about 15 months and under the Land Acquisition around 24 to 30 moths.

Since such a long time is taken to acquire the land, the process should get started much earlier or may be at the same time as the project is at the design stage. But actually the land acquisition plans are prepared very late.

There are quite a few reasons for the delay and some of these are:
Some Critical Issues Pertaining to Road Construction Industry
    • Outdated revenue maps form the basis for preparation of land acquisition plans. The records are often not been updated for a long period of time.
    • The land acquisition plans are often not realistic as the design consultants lack expertise to prepare such plans. They also do not carry out the alignment and ground verification.
    • There are frequent changes in the designs and alignments during implementation stage. In some cases, there are discrepancies in the project coordinates and the reference frames resulting in mismatch thereby resulting in redesign of the alignment.
    • The project authorities have to depend on the human resources from the revenue authorities, who are already over stretched and cannot, provide the required assistance on time.
    • In the absence of clear guidelines on providing compensation in special cases (including land owners with unclear titles or more than one owner), the settlement process takes a much longer time.
    • In addition to the above, the reasons for delay in resettlement are as follows:
    • Delay in finalization of the alignment and corridor of impact during project preparation stage
    • Delay in identification and finalization of the list of displaced persons. The list of title holders gets finalized after the declaration of award by the competent authority.
    • The alternative land for relocation during preparation stage is not firmed up
    • Construction and contract management issues:
    • Very weak contract management & enforcement environment.
    • The role of the Independent Engineer is not clear. Many of the Employers staff and domestic supervision consultants do not have adequate knowledge/ to understand the FIDIC conditions of contract (being followed in most of the NH and state highways projects).
    • Lack of the understanding between the Employers and the contractors that speedy completion of the projects is to both parties’ interest.
    • Lack of understanding of the contract conditions both by the Employers and the contractors.
    • Since the Employer is usually lacking in fulfilling his obligations under the contract, such as timely delivery of encumbrance free land, timely decision making on the variations, making payments on time, early activation of dispute resolution mechanism, his leverage on the contract enforcement gets eroded.
    • There is a resistance to acceptance of the responsibility in taking decisions, even when the Employer’s staff is convinced. This is because of a “fear psychosis” and the staff tries to pass on the buck.
    • There is lack of training imparted to the Employer’s, CSC’s & contractor’s staff on the general terms and conditions of the contract and the division of the parties’ rights, duties and obligations as per the contract. This results in lack of motivation for treating the project as a common goal and working as a “team”and all the parties try to shift the blame to others and no one tries to take the responsibility.
    • Due to dearth of construction management skills in the country, the contractor’s performance gets affected. This includes the contractor’s work planning, resource and workflow management, cash flow management and his overall project management.
    • The contractors generally quote low to win the contract. They normally have their eyes on making money through raising claims at a subsequent date knowing fully well that the Employer will certainly provide them many avenues to do so, particularly because of delay in making land available and delay in decisions, payments etc.
    • Since the role of the Independent Engineer is not very clear so the Engineer takes no responsibility.
    • The Engineer is not accountable as after the project is completed, he is simply not there.
Some Critical Issues Pertaining to Road Construction Industry
  • The supervision consultancy contracts are generally time based. This creates a perverse incentive to delayed decision making resulting in extension of the civil works and consequently in the extension of the CSC contract.
  • The staff in the CSCs is also not fully conversant with the FIDIC conditions of contract and is also not up to date with latest quality management techniques and new technologies. They are thus handicapped in managing contracts effectively with timely and quality decision making.
The delay in the construction has led to a large gap between the budget allocation and actual expenditure on the road construction in the country in the past few years. This gap has been in the range of 15-20%. About 70% of the contracts have been delayed and about 50% of the contracts had cost over runs of more than 25%. The mean delay was about 73% of the original contract completion time.

The need of the hour is to find an early solution to ensure timely completion of the road construction projects.

Acknowledgment

The World Bank: Indian Road Construction Industry: Capacity issues, constraints & recommendations.
NBM&CW September 2010
Performance of Thin White Topping (TWT) Overlay for NH-848

Performance of Thin White Topping (TWT) Overlay for NH-848

Vikas V. Thakar, MD, Pavetech Consultants India, presents the uses and advantages of TWT as a cost-effective treatment and a sustainable solution for rehabilitating and strengthening of flexible pavements, as seen in the NH-848 Nashik

Read more ...

REJUPAVE Technology for High RAP Recycling of Bituminous Pavement

REJUPAVE Technology for High RAP Recycling of Bituminous Pavement

Satish Pandey, Principal Scientist at CSIR-CRRI, New-Delhi, and Associate Professor, Academy of Scientific and Innovative Research, gives a brief overview of Hot Mix recycling process using bio-oil based rejuvenator REJUPAVE to facilitate

Read more ...

Safety Challenges On Indian Roads

Safety Challenges On Indian Roads

S.K. Nirmal, Secretary General, Indian Roads Congress, Director General (Road Development) & Special Secretary (Retd), MoRTH, gives an overview of India’s road network, causes of road accidents, and the safety measures and policies required

Read more ...

Dynapac Machines Deployed on Prestigious Palkhi Marg Project in Maharashtra

Dynapac Machines Deployed on Prestigious Palkhi Marg Project in Maharashtra

The Palkhi Marg holds deep significance as a pathway of faith for devotees of Lord Vitthal. Every year, thousands of ‘warkaris’ embark on a spiritual journey to the temple town of Pandharpur in Maharashtra. With the vision to create a Bhakti Marg and ensure

Read more ...

Delhi Vadodara Expressway Package-1 An overview

Delhi Vadodara Expressway Package-1 An overview

The Delhi-Vadodara Expressway is a part of the most anxiously awaited Delhi-Mumbai Expressway - the foundation stone for which was laid on March 8th 2019. Also referred to as the Delhi-Mumbai Industrial Corridor, it is planned as part of the Bharatmala

Read more ...

Bonded Rigid Pavement - A New Edge Concrete Pavement

Bonded Rigid Pavement - A New Edge Concrete Pavement

The exponential growth of the highway infrastructure in the past two decades has increased demand for long-lasting, durable pavements. Rigid pavements are suitable for heavily trafficked areas and are found to be performing satisfactorily with minimum

Read more ...

BRO Builds ‘Zero Fatality Corridors’ in Arunachal Pradesh

BRO Builds ‘Zero Fatality Corridors’ in Arunachal Pradesh

Through its unwavering commitment to road safety, eco-conscious practices, and visionary solutions, the Border Roads Organisation is elevating the standard of road infrastructure development in India. In Arunachal Pradesh, its contributions

Read more ...

Engineering Measures for Pothole Prevention

Engineering Measures for Pothole Prevention

Roads, pavements, and other paved surfaces have depressions in them called potholes which are caused by a variety of conditions. They not only present a serious risk to traffic and pedestrians, but also necessitate expensive repairs by local governments and

Read more ...

Pavement Marking Essential For Road Safety

Pavement Marking Essential For Road Safety

Vivek Singh, Founder, BuildStreet delves into the significance of pavement marking, its objective, and importance, with a focus on Hot Applied Thermoplastic paint - the predominant choice for road markings in India, its technical aspects, application methodology

Read more ...

GAEPL Achieves Record Paving of 100 lane-km in 100 hours

GAEPL Achieves Record Paving of 100 lane-km in 100 hours

Ghaziabad Aligarh Expressway Private Limited (GAEPL), under the guidance of Cube Highways, has set an example of speedy, safe, and sustainable road construction through research, integration of advanced technology, following best international practices

Read more ...

Indian Companies Delivering Projects Overseas

Indian Companies Delivering Projects Overseas

External affairs minister S. Jaishankar during his visit interacted with the workers and the senior staff, and lauded the role of Indian infra companies, saying that he was “impressed by their enthusiasm”. “Strong economics will complement shared values in taking

Read more ...

NHAI awards 6,003 km of highway projects in FY23

NHAI awards 6,003 km of highway projects in FY23

According to Motilal Oswal Financial Services, the infra project awarding activity picked up and gathered pace in Q4 of FY23, with NHAI awarding total projects of 6,003 km in FY23, much below its FY23 target of 6,500 km. The total value of projects awarded

Read more ...

Is the Indian Road Sector Navigating a Smooth Journey?

Is the Indian Road Sector Navigating a Smooth Journey?

This report covers the current state of the Indian Road Sector, performance of road projects under Hybrid Annuity Model, financial performance of major road developers, and the outlook for FY24. CareEdge Ratings analysed 235 HAM projects awarded between

Read more ...

Balanced Mix Design for Bituminous Mixes

Balanced Mix Design for Bituminous Mixes

As more than 90% of the roads in India have bituminous surfacing, a proper bituminous mix design also assumes significance for better performance of the bituminous roads. India is currently witnessing huge investments by the Indian Government towards

Read more ...

Sustainable Road Construction in Hilly Region

Sustainable Road Construction in Hilly Region

Siksha Swaroopa Kar, Principal Scientist, Amit Kumar, Technical Officer, Krishan, Technician, Flexible Pavement Division, CSIR-CRRI, New Delhi, discuss mechanized laying of cold bituminous layer, the mixer and paver that have been fabricated, and the effectiveness

Read more ...

Implementation of Road Maintenance Management System - Benefits & Technologies

Implementation of Road Maintenance Management System - Benefits & Technologies

The maintenance of road pavements is essential to ensure the safety, reliability, and sustainability of road networks. A road maintenance management system (RMMS) involves effective management of resources to optimize the life cycle of roads, reduce maintenance

Read more ...

Replacement of Steel Reinforcement with  Synthetic Fibre for Concrete Pavement & Floor

Replacement of Steel Reinforcement with Synthetic Fibre for Concrete Pavement & Floor

Manoj Didwania, Adani Total Gas Ltd, Dharamsinh Desai University (DDU-Nadiad), Cept University, presents a paper on the use of Macro Synthetic Reinforcement Fibre (MSRF) as full or partial replacement of Steel Reinforcement for Concrete Pavement

Read more ...

GTI® Reinforced Soil Slope System

GTI® Reinforced Soil Slope System

GTI® is involved in developing environmentally friendly construction products and systems, which are critical for achieving infrastructure growth in a sustainable manner. The company’s GTI® Sloping Fascia Unit and the new system GTI® Reinforced Soil Slopes

Read more ...

CRISIL: Debt to rise for road developers amid strong revenue growth

CRISIL: Debt to rise for road developers amid strong revenue growth

Sizeable equity commitments in under-construction projects and rising working capital requirement will increase the debt burden of road developers, though revenue growth will also be high in the next two fiscals driven by strong awarding and execution

Read more ...

To get latest updates on whatsapp, Save +91 93545 87773 and send us a 'Saved' message
Click Here to Subscribe to Our eNewsletter.