Tunnelling in Himalayas Where Uncertainty is Highly Certain

Brijesh Ashokbhai Wala, Engineer, National Highways and Infrastructure Development Corporation Limited (NHIDCL)
Brijesh Ashokbhai Wala, Engineer, National Highways and Infrastructure Development Corporation Limited (NHIDCL), presents the vagaries and challenges in underground construction, with case studies of projects constructed or planned in the complex geological terrains of the Himalayas, along with some mitigation measures and precautions to prevent accidents.

Orogenesis
Mountain belts which are created by continent-continent collision represent the most dominant and unique geologic features on the surface of the Earth. Some of the best examples of such continent-continent collision which lead to orogenesis are the Rockies and the Appalachian belt in North America, the Andes in the South America, the Ural Mountains in Central Eurasia, the Alps of Europe, and the Himalayas in Asia. The youngest and the most impressing of all such collisional belts is the Himalayan orogeny. The Himalayan mountain ranges are the product of collision between the India and Eurasian plate and a live example of collision mountain belt as the process of mountain building is still active, forming the highest range and plateau in the world.

Collision of Indian and Eurasian plate leading to formation of Himalayas
Tectonostratigraphic Subdivision of the Himalayas
The Himalayan mountain belt extends over 2500 km from northwest to northeast with a variable width of 230 to 330 km. The Himalayan terrain from South to North has been divided into sub-parallel tectonostratigraphic sub-divisions as under:
  • Sub-Himalaya or Outer Himalaya
  • Lower Himalaya or Lesser Himalaya
  • Higher Himalaya or Greater Himalaya
  • Trans Himalaya or Tibetan Himalaya
The dividing planes between these sub-divisions are the thrusts of regional dimension and varying tectonic activities and each subdivision has a characteristic stratigraphy which is not easily correctable with adjacent zones. From south to north, bounding faults are as follows:
  • Main Frontal thrust (MFT): Between Indo-Gangetic alluvial planes and Outer Himalayas.
  • Main Boundary Thrust (MBT): Between Outer Himalayas and Lesser Himalayas.
  • Main Central Thrust (MCT): Between Lesser Himalayas and Greater Himalayas.
  • Southern Tibetan Detachment system (STD): Between Greater Himalayas and Trans Himalayas.
Along each of these thrusts, tens to hundreds of kilometres of displacement between India and Asia have been accommodated, which in turn exert a major influence on landsliding and many devastating landslides are associated with movements along these thrusts.

Tunnelling in Himalayas
The government plans to build massive hydroelectric projects in the mountainous ranges to tap the renewable energy from gushing rivers; build road tunnels to connect the remote locations so that all-weather connectivity can be provided to the locals and the Armed Forces; and rail tunnels to connect the remotest location with the rail lines so that transportation, which once was a daunting task, will become smoother. All these underground structures have been planned in the complex geology of the Himalayas in the extreme vicinity of the tectonostratigraphic divisions mentioned above.

Tectonostratigraphic subdivisions of the Himalayas

Challenges encountered in various tunnelling projects
Tunnelling through the weak, fragile, and jointed rock masses of Himalayas is a challenging task. Tunnelling problems could be fault/thrust/shear zones, running ground conditions, heaving, squeezing and swelling, rock bursting, ground water inflow, hot temperature conditions and gases in rock, wedge/block failures, etc.

Due to an active tectonic zone, encountering fault/thrust/shear zones while tunnelling in the Himalayas is inevitable. A shear zone has sub-parallel walls in which deformations are localized as a result of folding, faulting, and thrusting. The shear zones, if combined with water ingress, (which occurs usually), hampers the progress of tunnelling considerably and, in some cases, there can be a complete break.

Dul-Hasti Hydroelectric project: The 390 MW Dul-Hasti hydropower project is a run-of-the-river scheme, constructed on river Chandra, a tributary of river Chenab that lies within the Lesser Himalayan Zone and is characterized by a unique plateau like feature with schists and gniesses on the western side and quartzites on the eastern side. The tunnel encountered a number of small and major faults and shear zones with crushed gouge material.

Figure 3 shows the muck flow when a shear zone was encountered during tunnelling. The incident happened after a shear zone was punctured, rendering the tunnelling extremely difficult. The shear zones were dipped steeply, striking oblique to the tunnel axis, and covering a length of 15 to 20 m along the tunnel alignment.

Muck flow from shear zones during tunnelling in Dul-Hasti hydroelectric project

Mostly, shear zones are associated with confined aquifers with high aquifer head. The shear zones along tunnel axis are usually projected from the geological mapping. However, in metamorphic terrain, due to being severely folded and faulted by tectonic events, the geology may significantly differ from surface geological mapping and hence, in such a terrain, advance probe hole technique during tunnelling has proved to be effective to ascertain the nature of the geological condition.

At Dul-Hasti, advance probe holes of 45 m length were found to be very effective during tunnelling in a shear zone closely associated with confined aquifers.

Installation of Umbrella Pipe roofing (b) Excavation by Multi Drift Technique

Tapovan - Vishnugad Hydropower project: The 520 MW Tapovan-Vishnugad hydropower project is a run-of-the-river scheme. It lies within Dhauliganga and Alaknanda valleys in Uttrakhand with high-grade metamorphic rocks of Central Himalayan crystalline series. Since the tunnel site has the main central thrust (MCT) in the vicinity, a number of small and big shear zones and faults were encountered while tunnelling, which resulted in a delay of 17 months. The situation was tackled by the following measures:
  • Advance cement grouting for face and crown stabilization.
  • Umbrella pipe roofs of 114 mm diameter, 15 m long @ 0.3 m spacing from SPL to SPL to ensure crown stability.
  • For seepage control, drainage pipes of 76 mm diameter were installed.
  • Excavation was done by breaking using Multi Drift Method.
  • Pull length restricted to 1 m.
  • Steel ribs (ISMB 250) at 0.6 m spacing were provided.
Atal Tunnel: The Rohtang Tunnel (commonly known as Atal Tunnel) is 8.8 km in length, extending from Dhundi to Teling in Himachal Pradesh and is situated in Higher Himalaya across Pir Panjal Range and Rohtang Ridge. The Seri-Nallah Fault Zone above tunnel alignment (shown in Figure 5) crosses the tunnel from the South Portal side and forms a contact between Phyllitic Schist and Migmatite. The 587 m long fault zone is heavily charged with water.

Google image of Ser-Nallah Fault zone (b) Actual photo of Seri Nallah Fault Zone showing alignment of tunnel

The tunnelling work started in August 2010 and progressed well upto 1902 m, but in December 2011, the quality of rock encountered started deteriorating, resulting in long delays and slow advancements. Excessive deformation due to squeezing ground condition occurred subsequently. The project was delayed by approximately 5 years due to the geological surprise encountered in the form of the Seri Nallah fault zone (Figure 6).

Muck flow, and (b) Excessive deformation were the actual problems faced while tunnelling in Seri-Nallah zone

The mitigating measures included:
  • Excavation in segmental phases
  • Installation of double rows of 89 mm diameter pipe roofing umbrella
  • Probe hole drilling for assessment of advance geology
  • Tunnel Seismic Prediction (TSP) tests conducted on the face to get a better understanding of muck flow condition and the rock strata.
To overcome the flowing condition and extremely poor geological conditions, P-5 system has been followed to tackle such adverse conditions. P-5 system consists of the following operations for the purpose of excavation:
  • Plug
  • Probe
  • Pressure Relief
  • Protection of roof
  • Pre-Grout and Support
Double row pipe roofing (b) Tunnel seismic prediction

Squeezing, heaving, and swelling
At depth, the state of stress within the rock mass is disturbed due to tunnel excavation. The stresses are redistributed with time to achieve a new state of equilibrium - commonly known as the “natural healing process” of rock mass. When the stresses are low and less than in-situ rock strength, there are no tunnel stability problems, however, when the stresses exceed the in-situ strength, it initiates the process of progressive failure around the periphery of the tunnel opening. The failure of rock mass due to overstressing and movement of the failed rock mass into the tunnel opening is called squeezing.

Maneri Bhali project: The Maneri Bhali project experienced severe squeezing within a 40 m length of 6 m diameter tunnel. The highly crushed, pulverised and thick contact of metabasics and the qaurtzites were highly strained due to active tectonic folding. To overcome the problem, the horse-shoe section was changed to circular section and instruments installed to monitor the troubled zone.

Nathpa-Jhakri project: In the HRT of Nathpa-Jhakri, highly converging strata has been encountered due to high ground stresses where quartz mica schist striking sub-parallel to tunnel were encountered. They were reflected in the form of cracks in the shotcrete, bending and buckling of steel ribs and reduction of tunnel section. To mitigate the risky situation, the problem was tackled by over-excavation and supporting it with steel ribs.

To overcome the effect of excessive deformation and squeezing rock mass, the rate of deformation must first be analysed by continuous monitoring in the particular region. In addition to that, yielding supports and pressure relief holes (as shown in Figure 9) should be applied with remedial measures during excavation to control the deformation.

Severe squeezing of tunnel

Rock bursting, spalling, and slabbing
Rock bursts or spalling are caused by overstressing of brittle, massive rocks often at a depth more than 1000 m below surface. At shallower depths, these failures can be induced where high horizontal stresses or strongly anisotropic stresses are acting.

Parbati Hydroelectric Stage II: This project lies in the Lesser Himalayan region. Being very close to the main central thrust (MCT), the rocks along HRT have undergone intense compression and are therefore folded, faulted, foliated and jointed - typical characteristics of Himalayan rocks. The excavation was done by open-face hard rock TBM of 6.8 m diameter for a particular section comprising of granites/gneissose granites followed by quartzites.

Due to the presence of four primary joint sets and random joints, a large block of 6 m * 2.5 m separated from the crown, forming a cavity. As the area was inaccessible, the rock bolter could not reach the height of cavity and pre-grouting was not possible because of tight joints. To tackle this, ring beams were installed, the rock was supported with channels and girders, and the cavity was backfilled with concrete. The whole process delayed the project by more than three weeks. With this experience, modifications were made in the TBM by mounting an extension drilling system. The next 250 m created similar problems of wedge/block failure resulting in overbreaks of more than 5m which were backfilled with concrete.

Linear stress controllers (Yielding supports) applied to control the deformation

Conclusion
The case studies indicate that tunnelling in the tectonically active Himalayan terrain (which is characterized by widely varying geology with folds, faults, thrusts and shear zones along its entire belt), geological uncertainties cannot be ruled out. The problems occurring due to geological surprises can be minimised and mitigated by geological investigations and adopting advanced measures.

Before the tendering process of any tunnel project, a detailed project report (DPR) should be prepared by performing geotechnical investigations like bore logging along the alignment proposed to understand the in-situ stress conditions in the rockmass and pre-construction surveys like Airborne Electro-Magnetic survey (AEM), Seismic Refraction tests and Electrical Resistivity tests to understand the groundwater conditions and rock mass properties be carried out adhering to standard technical specifications. The report should comprise of detailed test results of all the investigation methods mentioned above. This will facilitate easier recognition of the ground conditions and prepare the stakeholders of any uncertainty that can be encountered during the execution of the project, which will help save resources.

References
  • Carter, T. G. (n.d.). Himalayan Ground Conditions challenge innovation for successful TBM Tunnelling.
  • Kumar Yadav, V., Kumar Angra, P., & Kumar, V. (n.d.). Indian Geotechnical Conference-2010.
  • Rao, S. K. (2017). Necessity of NATM tunnel in Himalayas - A Case Study of Rohtang Tunnel. https://www.researchgate.net/publication/320729563
  • Karki, S., Chhushyabaga, B., & Khadka, S. S. (2020). An Overview of Design and Construction practices of Himalayan Hydropower tunnels. Journal of Physics: Conference Series, 1608(1). https://doi.org/10.1088/1742-6596/1608/1/012008
  • Tunnelling in the Himalayan Region: geological problems and solutions. (n.d.). https://www.researchgate.net/publication/269407897
Click Here
To Know More or to Contact the Manufacturer
Please let us know your name.
Invalid Input
Please let us know your Designation.
Please let us know your Contact Number.
Please let us know your email address.
Please brief your query.
Our other Value-Added Services:

To receive updates through e-mail on Products, New Technologies & Equipment, please select the Product Category(s) you are interested in and click 'Submit'. This will help you save time plus you will get the best price quotations from many manufacturers, which you can then evaluate and negotiate.

Invalid Input
Invalid Input
Invalid Input
Anirban Sen, Business Line Manager – Underground Division, Epiroc Mining (India), explores the technologies, methods and benefits of modern intelligent face drilling equipment, the reasoning behind selection of ‘smarter’ face drills

Read more ...

This case study of the Sewa H.E. Project (120MW) in the Kathua district of Jammu and Kashmir, covers the planning process and various construction features of a 10.02km long, 3.3m diameter horseshoe shaped concrete lined tunnel

Read more ...

Strabag AG implements complex construction projects, particularly in tunneling and infrastructure development, and is represented in around 30 countries worldwide. It has been active in the fields of building construction, civil

Read more ...

Construction is underway on a tunnel as part of a bypass to relieve traffic for communities in Toggenburg, Switzerland. For Doka’s formwork experts, keeping in view the conditions of this project, their new, rentable tunnel system

Read more ...

On 22nd September 2021, hard rock/slurry TBM Urja (DZ670) manufactured by China Railway Construction Heavy Industry Cooperation Limited (CRCHI) achieved a breakthrough from the Cantonment Station to the Shivaj Nagar Station

Read more ...

Hard Rock Tunnel Boring Machine (TBM) is the first choice for the construction of hard rock tunnels because it is a fast, safe, and environmental-friendly construction method. As overburden increases, the ground stress of

Read more ...

The Mumbai-Nagpur Expressway is delayed until 2022 due to Covid-19. In the meantime, a machine with remarkable operational reliability was specially flown in from the supplier in Germany to help speed up the project.

Read more ...

US Tunnel Boring Equipment manufacturer, The Robbins Company, will continue to make owning and operation of its TBMs cost-effective for Indian contractors. It will also explore newer vistas of engagement with

Read more ...

Geo Constech Druc Svelta Resin Capsules
Geo Constech (GCPL), one of the leading solution providers of material and technology, introduces Druc-Svelta, Druc-Si’ment Cap, Druc-Stone, Druc-Colata 41, and Druc-Tyrocrete. With an objective

Read more ...

Horizontal Bores
Trenchless construction is a method of laying services under the ground without disturbing the surface structures. The imported underground horizontal drilling machines are available

Read more ...

Mobile Sinking Winch
The "DEEP SHAFT COAL MINE" consists of essentially two vertical shafts, one to hoist men and materials, and the other for winding coal from deeper seems."MINE SHAFT" surface structures

Read more ...

Slag Crushed in Crusher
For the last 20 years, the use of by products of various origins in the production of concrete has become an increasingly widespread practice in the world. The main advantages are all the elimination of scraps

Read more ...

Soil Stabilization
Sub-grade soil stabilization is one of the primary and major processes in the construction of any highway. The aim of this research paper is to formulate a model to predict variation in the values of CBR

Read more ...

Building Resistant to Earthquake
Studies on hidden beams have been carried by various researchers. Its use for high rise buildings with raft foundation is of very useful. However, its use for low rise buildings may not be effective to a considerable

Read more ...

Sustainability Cement Perspective
The cement industry is one of two primary industrial producers of carbon dioxide (CO2), creating up to 5% of worldwide man-made emissions of this gas, of which 50% is from the chemical process

Read more ...

World Trade Centre Twin Tower
The failure and collapse of civil engineering structures in general and buildings in particular has become a very common phenomenon in last few years. This paper highlights the new reasons of failure

Read more ...

Polluting Cement
By the end of the Nineteenth century, the British rulers had imported 'Cement' to India and commenced discouraging the method of using freshly ground lime for masonry construction that was in vogue

Read more ...

Volvo Trucks Safety Systems
Since 1927, traffic safety has always been one of Volvo Trucks' core values and the company is currently well to the fore when it comes to safety development. Tiredness alerts, lane change assistance and help

Read more ...

Cement based construction industry plays a vital role in infrastructure development of a country. Cement concrete is the backbone material of construction industry. Water plays an important role in the production

Read more ...

×
Sign-up for Free Subscription
'India Construction Week'
Weekly e-Newsletter on Construction Industry
Get the latest news, product launches, projects announced / awarded, government policies, investments, and expert views.