Mammoet Uses LTM 11200 Crane to Replace Roof-Mounted Façade Cranes in The Hague


Determining the Best Crane for the Job

Mobilizing this crane—featuring the world’s largest telescopic boom—to the heart of the city was no small feat. The engineering team also determined that there was only one setup location that would allow the crane’s boom to reach both buildings.
“This was due to the Y-frame,” explains Stefan Plugge, Project Manager at Mammoet. “We had to find a position that allowed us to stay clear of the buildings and the viaduct. From the identified position, the crane could service both buildings—avoiding the need to demobilize and relocate it, thereby saving time and minimizing disruption.” During setup, the team used only the space required, further reducing disruption. For the first two days, a smaller assembly area was sufficient. Only on the third day—when the boom had to be assembled on the ground—was the area temporarily expanded. This enabled a key road to be closed for just one day instead of three.
Tall Lifts in a Complex City

The team established two lifting zones with defined boundaries: one for smaller parts (up to three meters) and another for larger components measuring up to 10.5 meters in length.
Working within these zones enabled only short-term closures of a nearby canal and adjoining road during the lifting phase. Additional safety measures were strictly implemented.

“We agreed with the client that all items would be attached using fixed lifting points,” adds Plugge. “No items were lifted using slings or alternative methods. We also set a low maximum allowable wind speed for operations.” It was also determined that the roofs were not strong enough to withstand the impact of heavier components in case of a fall. Therefore, a crash deck was installed on each roof before any lifting operations began. As is typical in a governmental hub, The Hague presents a complex environment for high-altitude heavy lifting, requiring detailed permitting, lifting strategies, and safety planning. Mammoet provided all necessary documentation promptly to keep the project on schedule. The team successfully minimized disruption while completing these high lifts safely and efficiently in a challenging urban setting.
Published on:
20 March 2026
Share:
We Value Your Comment




